Question Submitted:
1) Will a 120 day lead time be acceptable?
2) Will products be used in an indoor or outdoor/semi-outdoor setting?
3) Do the garage-style racks need to be hot-dip galvanized to protect against rust/corrosion?
4) Is assembly of the racks and setting up of the space with all equipment required upon delivery?
5) Can the unit provide forklifts and/or other equipment and manpower to assist with offloading upon delivery?
6) Will drop shipping of certain items be acceptable or does the customer wish to have all items consolidated and shipped at once from the same location?
Response Received:
1. 120 day lead time is acceptable
2. This equipment will be used both indoors and outdoors.
3. Yes, racks will need to be protected against rust.
4. Set-up & installation will be handled by the unit.
5. The unit will be able to provide MHE and additional manpower at the time of delivery.
6. Delivery of the complete order is preferable to individual components being sent overtime.
|
Unison Marketplace Process Help
Help and Training page which includes training videos, interactive help, and more. A link can also be found on the top right of every page, after log in.
For additional information, please contact:
Marketplace Support
Tel: (877) 933-3243
Contact Marketplace Support
For additional information, please contact:
Marketplace Support
Tel: (877) 933-3243
Contact Marketplace Support