Questions & Responses Released to All Sellers
![]() |
Buy #: 1151538_01
|
Question Deadline:
08/21/2023 16:00 ET
|
Question Count: 2
|
![]() |
Buy #: 1151538_01
|
Question Deadline:
08/21/2023 16:00 ET
|
Question Count: 2
|
Question Submitted:
Who is responsible the fueling of the generators?
Response Received:
Government will be responsible.
|
Question Submitted:
Could you kindly consider extending the closing date by a week, considering that this is 1000KW rotating equipment with a potential acquisition cost of over quarter of a million USD.
Response Received:
Sorry can not extend! Reminder this is a lease of that equipment. Government will not be buying this equipment at this time.
|
![]() |
Buy #: 1151538
|
Question Deadline:
08/18/2023 11:00 ET
|
Question Count: 1
|
![]() |
Buy #: 1151538
|
Question Deadline:
08/18/2023 11:00 ET
|
Question Count: 1
|
Question Submitted:
A few questions to get your quote correct: What is the estimated target date for the job? How long for the rental? How many hours will you be running the generators per week? What voltages and amperage are you working with? How much cable do you need? You need transportation and set up? Do you need fuel service?
Response Received:
Target date is in teh Statement of work. Transporation set up, training are also required. Will be running 24/7. No fuel service needed. Delivery full.
|
Unison Marketplace Process Help
Help and Training page which includes training videos, interactive help, and more. A link can also be found on the top right of every page, after log in.
For additional information, please contact:
Marketplace Support
Tel: (877) 933-3243
Contact Marketplace Support
For additional information, please contact:
Marketplace Support
Tel: (877) 933-3243
Contact Marketplace Support