Question Submitted:
We are finding it impossible to find something with similar specs with this requirement.
Response Received:
I am working to revise the specifications for CLIN 1, as they are incorrect. Please standby for an amendment to this requirement.
Question Submitted:
Do you have any manufactures for item 1 that I can check out from an bids coming in? Cannot match the specs anywhere.
Response Received:
A revision has been made in the form of an amendment to the requirement, due to incorrect specifications for CLIN 1. Please review all of the highlighted changes within the amendment.
Question Submitted:
Can you provide any more info for CLIN 1.
Response Received:
A revision has been made in the form of an amendment to the requirement, due to incorrect specifications for CLIN 1. Please review all of the highlighted changes within the amendment.
Question Submitted:
Do you have any manufactures for item 1 that I can check out? I cannot match the specs anywhere.
Response Received:
A revision has been made in the form of an amendment to the requirement, due to incorrect specifications for CLIN 1. Please review all of the highlighted changes within the amendment.
Question Submitted:
Can we bid flashlights made outside of the US? I am finding it difficult to find a company in the US that could supply a 220 volt for this order request.
Response Received:
Yes, the place of manufacture can be outside of the US. However, from the combined synopsis/solicitation's "technical compliance matrix", the place of manufacture must be in accordance with FAR 25.4 - Trade Agreements.
Question Submitted:
1. Will the quantity of 500 each per period of performance need to be delivered in 1 complete shipment or will there be multiple deliveries? 2. If multiple deliveries are expected, what is the estimated quantity per delivery?
Response Received:
Thank you for your questions: #1. It is acceptable for multiple deliveries to be completed 30 days after the signed award. #2. There is no estimated quantity per delivery. However, in accordance to the Combined synopsis/solicitation all 500 flashlights (per line item) for the Base year are to be delivered no later than 30 days after the signed award.
Question Submitted:
Period of Performance Base: 09/30/2019 - 09/30/2019 Option 1: 09/30/2019 - 09/30/2019 Option 2: 09/30/2019 - 09/30/2019 can you verify this info it does not match the info provided as it should be 2020-2021 and 2021-2022
Response Received:
Yes, you are correct. The correct period of performance is for one base year + two (2) option years. See below: Base Year: 09/20/2019 - 09/19/2020 Option Year 1: 09/20/2020 - 09/19/2021 Option Year 2: 09/20/2021 - 09/19/2022
Question Submitted:
1. Minimum output of 10 LED's and 85 lumens may be in error? Most multiple LED flashlights have very high lumens. Is this correct? 2. The bezel diameter is not a typical size by most manufactures. Is this an error? 3. The requirement states the charger voltage at 220V. Most chargers are either 12VDC or 120VAC. Is this 220V requirement correct?
Response Received:
1. Yes, the requirement only states the minimum; higher lumens may be acceptable, provided that the other specifications are met. 2. The Bezel diameter is correct as stated. However, there are other acceptable bezel diameters, provided that the other specifications are met for the requirement. 3. The 220V requirement is correct. The 220V is a standard voltage for Ukraine and Europe.
Unison Marketplace Process Help
Help and Training page which includes training videos, interactive help, and more. A link can also be found on the top right of every page, after log in.

For additional information, please contact:

Marketplace Support
Tel: (877) 933-3243
Contact Marketplace Support