Question & Responses for Buy # 1026193

Questions & Responses Released to All Sellers
Buy #: 1026193
Question Deadline:  None
Question Count: 2
Buy #: 1026193
Question Deadline:  None
Question Count: 2
Question Submitted:
Q1. Does all wiring required existing on present controls and available up to the racks to be provided ? Q2. Are the terminations to plugs and jacks or directly to the discrete controls ? Q3. Do all chambers have the same capabilities that permit the same setup programs on all controllers ? Q4. Is there any schematic documentation required ?
Response Received:
A1.All chambers are operational with the existing wiring/controllers. New equipment will be mounted in the same/adjacent panel location. The new equipment has the same functional requirement. The contractor is responsible for local wiring changes at the control panel, but not remote wiring. A2. Existing connections are bare wire or terminal connections to the instruments, no plugs. A3. All chambers use liquid CO2 cooling and electric heating and have similar configurations. The controllers/safety are mounted remotely from the chamber. The original chambers are from various manufacturers, however the contractor will be provided access to equipment documentation if available. A4.Contractor revision of the existing equipment wiring schematic/documentation is not required.
Question Submitted:
I could quote you on line item 1 and 1 only. I’m not familiar with line item 2 or 3. If that is satisfactory, please let me know and I’ll send you a quote. Thank You
Response Received:
Contractor is required to provide all items (0001 to 0004)including installation for contract award.
Unison Marketplace Process Help
Help and Training page which includes training videos, interactive help, and more. A link can also be found on the top right of every page, after log in.

For additional information, please contact:

Marketplace Support
Tel: (877) 933-3243
Contact Marketplace Support